Our team is wrapping up another productive week at the latest major Starbucks project at Gus Thomasson and Ferguson in Dallas, TX.
We are currently in week 14 of this project. On the interior, we are finishing up interior wall finishes.
On the exterior, this week’s focus was the drive-through turnbuckles and back door awnings. This week, we will continue with the exterior aluminum cladding and prepare for the stucco and concrete.